WESTERN QUEEN PROJECT
DEVELOPMENT UPDATE
ASX RELEASE I 24 AUGUST 2026
ASX:RTR
KEY POINTS
• Approvals and Permits - Groundwater Extraction Licence recently granted by DWER. The Mine
Development and Closure Proposal is the last outstanding major approval.
• Pit Dewatering - Preferred contractor engaged, pumps and pipework ordered and formal agreement being
finalised.
• Mining Contractor - Discussions continue with potential underground mining contractors who have
expressed interest in the Project and submitted Expressions of Interest.
• Updated Scoping Study - Work is underway to update the November 2025 Scoping Study. Revisions will
incorporate the June 2026 Mineral Resources upgrade, a revised mining schedule, final terms of the Gylden
and Kirkalocka Gold Toll Milling and Blending Agreement and refreshed capital and operating cost
estimates.
• Project Financing - Following the completion of the updated Scoping Study potential project debt
providers will be formally invited to submit financing term sheets.
• Personnel - GM Operations, Jake Campbell, commenced on 10 August.
• Operational Readiness - An operational readiness plan is currently being drafted ahead of the CY2026
pre-development works which include pit dewatering and cleaning up the open pit (ramp and floor).
• Bankable Feasibility Study and Decision to Mine - Subject to positive results from the Updated Scoping
Study and receipt of acceptable indicative financing terms, the Company will proceed to complete a
Bankable Feasibility Study, which will support a Decision to Mine, targeting the December quarter 2026.
Peter Harold, Managing Director and CEO commented:
“We are 100% committed to getting Western Queen into production as soon as possible. The first major task is
dewatering of the Western Queen South open pit, and we are pleased to report that we have recently received the
Groundwater Extraction Licence to enable this to commence. The Mine Development and Closure Proposal is the
only major outstanding approval required before we can start underground pre-development works.
Once the pit is dewatered, we can commence underground mine development, with first ore expected to be
delivered to Kirkalocka approximately six months after the portal is cut.”
2
Rumble Resources Limited / ASX:RTR
ABN 74 148 214 260
www.rumbleresources.com.au
Head Office
Level 1, 16 Ord St
West Perth, WA 6005
Contact Us
T. +61 8 6555 3980
E. info@rumbleresources.com.au
ASX:RTR
Rumble Resources Limited (ASX: RTR) (“Rumble” or the “Company”) is pleased to provide this update on the
proposed underground mine development at the Western Queen Gold and Tungsten Project (“Western Queen” or
the “Project”). Western Queen is located 90km northwest of Mount Magnet within the Yalgoo Mineral Field of
Western Australia. Rumble holds 100% equity in the Project.
The Project is comprised of two contiguous mining leases (M59/45 and M59/208) for a total area of 9.8 km².
Surrounding the Western Queen Project is the Wardawarra Project (100% Rumble). The Wardawarra Project
consists of three granted exploration licences (E20/967, E59/2816 and E59/3012).
Historical production at Western Queen totalled 880,000t @ 7.6 g/t Au for 215,000oz from two deposits. The
Western Queen Central Mine produced 660,000t @ 8.9 g/t Au for 189,500oz and the Western Queen South
Mine produced 220,000t @ 3.6 g/t Au for 25,500oz.
In June 2026, Rumble announced an updated Mineral Resource Estimate 5.13Mt @ 2.6g/t Au for a total of
433,600oz contained gold1
. This includes Indicated Resources of 2.46Mt @ 2.9g/t Au for 227,700oz
contained gold.
Rumble has entered into a Toll Milling and Blending Agreement with Gylden Resources Pty Ltd (“Gylden”) and
Kirkalocka Gold SPV Pty Ltd for material from Western Queen to be toll treated at Gylden’s Kirkalocka plant,
approximately 180km southeast of Western Queen.2. Gylden is currently refurbishing the plant, which is scheduled
to come on stream in the second half of 2026.
Figure 1 - Location of Western Queen mining leases in relation to Kirkalocka
1
ASX release date 24 June 2026 “Western Queen Gold Resources upgraded to 443koz with 228koz now in Indicated category and a new
high-grade zone of 53koz @ 11.3g/t gold”
2 ASX release dated 19 May 2026 “Toll Milling and Blending Agreement for Western Queen gold ore executed with Gylden and Kirkalocka
Gold”
3
Rumble Resources Limited / ASX:RTR
ABN 74 148 214 260
www.rumbleresources.com.au
Head Office
Level 1, 16 Ord St
West Perth, WA 6005
Contact Us
T. +61 8 6555 3980
E. info@rumbleresources.com.au
ASX:RTR
Figure 1 - Western Queen location in relation to Kirkalocka
November 2025 Scoping Study
The Western Queen South underground mine Scoping Study (or “the Study”) was undertaken by an independent
mining consultant, Baybridge Mining Services, with the results of the Study released in November 20253. The Study
was based on initially mining only a portion of the defined Western Queen South Resource from underground and
processing the ore at a third-party processing facility. Key findings from the Study were:
• Production Target of 617kt at 2.95g/t for 58.5koz contained gold over a two-year period;
• Free cash flow of $133M, NPV (at 8% discount rate) of $112M and an IRR of 370% at a gold price of
A$5,540/oz (compared to the current spot gold price of circa A$6,150/oz);
• All in sustaining costs of A$2,970/oz gold;
• Simple underground mine design utilising uphole stoping (refer Figure 2);
• Very low upfront pre-development capital of less than $10M; and
• Only 29% of the July 2025 Mineral Resource at Western Queen South was included in the Production
Target of this Study, providing additional opportunities to extend mine life.
Figure 2 - Western Queen South underground mine design - 617kt @ 2.95g/t for 58.5koz
Updated Scoping Study
Rumble is presently working on an Updated Scoping Study for Western Queen. The Updated Study is on track for
delivery in late September 2026, ahead of a Bankable Feasibility Study.
The Updated Scoping Study will incorporate more of the Western Queen South Resources defined in the June
2026 Mineral Resource Estimate, as well as the new high-grade zone of 145kt @ 11.3 g/t Au for 52,500oz
situated directly below the historical underground workings at Western Queen Central (Figure 3).
3
ASX release date 27 November 2025 “Western Queen South Scoping Study Highlights Robust Underground Mining Project”
4
Rumble Resources Limited / ASX:RTR
ABN 74 148 214 260
www.rumbleresources.com.au
Head Office
Level 1, 16 Ord St
West Perth, WA 6005
Contact Us
T. +61 8 6555 3980
E. info@rumbleresources.com.au
ASX:RTR
Figure 3 - Conceptual underground mine design to mine bulk of current WQ South and Central Resources
Mine Development Progress
The Company continues to make significant progress towards commencement of gold production at Western
Queen. Progress against key milestones include:
• Ore Processing - Toll Milling and Blending Agreement with Gylden Resources Pty Ltd (“Gylden”) and
Kirkalocka Gold SPV Pty Ltd executed.
• Mineral Resource Estimate - Updated Resource estimate of 5.13Mt @ 2.6g/t Au for a total of 433,600oz
contained gold released 24 June 2026.
• Permitting & Approvals - to date the following permits and approvals have been received:
Works Approval
Native Vegetation Clearance Approval
Groundwater Extraction Licence
The Mine Development and Closure Proposal remains outstanding
• Pit Dewatering - Preferred contractor engaged, pumps and pipework ordered, and formal agreement being
finalised.
• Mining Contractor - Discussions continue with potential underground mining contractors who have
submitted ‘Expressions of Interest’.
• Updated Scoping Study - Work is underway to update the November 2025 Scoping Study. Revisions will
incorporate the June 2026 Mineral Resources upgrade, a revised mining schedule, final terms of the Gylden
and Kirkalocka Gold Toll Milling and Blending Agreement and refreshed capital and operating cost
estimates.
• Project Financing - Following the completion of the updated Scoping Study potential Project debt
providers will be formally invited to submit financing term sheets.
• Personnel - GM Operations, Jake Campbell, commenced on 10 August. Jake is a highly experienced
mining executive with more than 15 years’ in underground mining, specifically in project development,
commissioning and operations.
5
Rumble Resources Limited / ASX:RTR
ABN 74 148 214 260
www.rumbleresources.com.au
Head Office
Level 1, 16 Ord St
West Perth, WA 6005
Contact Us
T. +61 8 6555 3980
E. info@rumbleresources.com.au
ASX:RTR
• Operational Readiness - In anticipation of the commencement of pre-development works including pit
dewatering and cleaning up the open pit (ramp and floor) later in CY2026, an operational readiness plan is
being prepared.
• Bankable Feasibility Study & Decision to Mine - Subject to positive results from the Updated Scoping
Study and receipt of acceptable indicative financing terms, the Company will proceed to complete a
Bankable Feasibility Study, which will support a Decision to Mine, targeting the December quarter 2026.
Potential Tungsten Revenue Stream
Rumble announced a maiden tungsten Mineral Resource Estimate of 4.31Mt @ 0.31% WO3 for 13.2kt WO3
4 in
August 2025. The tungsten mineralisation at Western Queen occurs within a prograde skarn stage that lies closely
adjacent to the gold mineralisation. Tungsten mineralisation at Western Queen remains open in all directions.
Recent metallurgical testwork on the scheelite material at Western Queen has confirmed it can be upgraded to a
concentrate containing 48% WO3 at a 45% recovery via a simple and conventional gravity circuit5.
A Scoping Study will be carried out on the tungsten once the gold Bankable Feasibility Study is completed.
-ENDS-
Authorisation
This announcement was approved for release by the Board of the Company.
For further information please refer to the Company’s website www.rumbleresources.com.au or contact
info@rumbleresources.com.au
Peter Harold
Managing Director & CEO
Peter Venn
Technical Director
Trevor Hart
Chief Financial Officer
About Rumble Resources
Rumble Resources is an Australian based exploration company, listed on the ASX in July 2011. Rumble was established with
the aim of adding significant value to its selected mineral exploration assets and to search for suitable mineral acquisition
opportunities in Western Australia.
Rumble has a unique suite of resources projects including the Western Queen Gold-Tungsten Project which is being developed
to deliver near term cash flow from the existing underground resources and resource growth through future exploration success.
In addition, the discovery of the Earaheedy Zinc-Lead-Silver Project has demonstrated the capabilities of the exploration team
to find world class orebodies.
Previously Reported Information
The information in this report that references previously reported exploration results, Mineral Resource estimates,
Production Targets, forecast financial information and study results is extracted from the Company’s ASX market
announcements released on the dates noted in the body of the text where those references appear. The previous
market announcements are available to view on the Company’s website or on the ASX website at www.asx.com.au.
The Company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcements and, in the case of estimates of Mineral Resources, that all material
assumptions and technical parameters underpinning the estimates continue to apply and have not materially
changed. The Company further confirms that all material assumptions underpinning the Production Target and
forecast financial information disclosed in the November 2025 Scoping Study continue to apply and have not
materially changed. The Company confirms that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the original market announcements
4
ASX release date 11 August 2025 “Maiden Tungsten Resource of 13,200 tonnes of WO3 highlights the exceptional potential of the Western
Queen Project”
5
ASX release date 26 March 2026 “Excellent Metallurgical Results for Western Queen Gold and Tungsten Project”
6
Rumble Resources Limited / ASX:RTR
ABN 74 148 214 260
www.rumbleresources.com.au
Head Office
Level 1, 16 Ord St
West Perth, WA 6005
Contact Us
T. +61 8 6555 3980
E. info@rumbleresources.com.au
ASX:RTR
Disclaimer
This report contains certain forward-looking statements and forecasts, including possible or assumed reserves and
resources, production levels and rates, costs, prices, future performance or potential growth of Rumble Resources
Ltd, industry growth or other trend projections. Such statements are not a guarantee of future performance and
involve unknown risks and uncertainties, as well as other factors which are beyond the control of Rumble Resources
Ltd. Actual results and developments may differ materially from those expressed or implied by these forward-looking
statements depending on a variety of factors. Nothing in this report should be construed as either an offer to sell or
a solicitation of an offer to buy or sell securities. This document has been prepared in accordance with the
requirements of Australian securities laws, which may differ from the requirements of United States and other
country securities laws. Unless otherwise indicated, all ore reserve and mineral resource estimates included or
incorporated by reference in this document have been, and will be, prepared in accordance with the JORC
classification system of the Australasian Institute of Mining, and Metallurgy and Australian Institute of Geoscientists.
Share your feedback
Discover