ASX ANNOUNCEMENT
27 November 2025
Western Queen South Scoping Study Highlights
Robust Underground Mining Project
Highlights
• The Scoping Study on mining Western Queen South demonstrates a robust underground mining
project with low capital and operating costs which could generate very strong cashflow
• Rapid start up with first ore potentially within six months of commencing decline development
• Ore can be toll treated at Gylden Resource’s Kirkalocka plant, approximately 180km southeast of
Western Queen which is scheduled to come on stream in the second half of CY2026
• A 20,000m diamond drill program is underway aimed at infilling and extending the recently upgraded
370koz @ 3.1g/t Au1
Mineral Resource Estimate, which if successful could significantly increase the
production profile and mine life
• Work continues on the tungsten which could add a very valuable co-product revenue steam to
Western Queen in a relatively short time frame
Rumble’s Managing Director Peter Harold commented “It is a fantastic result. The Western Queen South
Scoping Study clearly demonstrates the incredible value of the underground development option at our
Western Queen Gold Project. Importantly, the upfront capital required is relatively small. Given the scoping
study only considers the Western Queen South resource there is huge upside to increase mine life with the
addition of the Western Queen Central resource which could be accessed from the same decline.
Our primary focus now is getting Western Queen into production as soon as possible. To that end we continue
to progress the approvals process on the existing Mining Leases and are negotiating an ore tolling agreement
with Gylden Resources, the owner of the Kirkalocka plant which is due to be operational in the second half of
2026.
In addition to our plans to start mining Western Queen as soon as possible we are currently undertaking a
20,000m diamond drilling program aimed at increasing the size and confidence of the mineral resources, both
gold and tungsten, at Western Queen.
Once the current diamond drill program is completed and assuming there is an upgrade in Indicated Resources
at both Western Queen South and Central this could lead to a significant increase in material that could be
mined from underground.
The metallurgical testwork being undertaking on the tungsten material will provide important information on
how we may be able to monetise that resource which is located proximal to the gold mineralisation.”
1 Refer to Rumble ASX release 23 July 2025 “Significant Increase to Western Queen Resources to 370koz @ 3.1g/t Au”
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 2
Rumble Resources (“Rumble” or the “Company”) (ASX: RTR) is pleased to report results from the Westen Queen
South Scoping Study (the “Scoping Study” or “the “Study”) completed by an independent mining consultant,
Baybridge Mining Services, on the Western Queen Gold Project (“Western Queen” or the “Project”). Western
Queen is located approximately 90km Northwest of Mt Magnet in Western Australia and contains resources
totalling 370,000oz Au at 3.1g/t Au. The Study is based on initially mining only a portion of the Western Queen
South Resource from underground and processing the ore at a third-party processing facility.
The shallow, high-grade, orogenic gold deposits at Western Queen were first discovered and developed in the
1930s. Up until the last open cut operations were completed by Ramelius Resources in 2014, historical
production from the Western Queen Central and South pits totalled 880,000 tonnes at 7.6 g/t Au for 215,000
ounces. Western Queen sits on a major regional shear system, similar to the structurally controlled high grade
deposits at Ramelius’ 2.32Moz Dalgaranga Project, 48km to the southeast. Western Queen remains largely
untested along strike and at depth, presenting strong exploration upside.
Key findings from the Western Queen South Scoping Study are as follows:
• The Study only considers the Western Queen South Resource
• The Production Target for Western Queen South is 617kt at 2.95g/t for 58.5koz contained gold;
• Robust economics with free cash flow of $133M, an NPV (at 8% discount rate) of $112M and an IRR of
370% at a gold price of A$5,540/oz2
;
• All in sustaining costs of A$2,970 per oz gold;
• Simple underground mine design utilising uphole stoping due to simple, steep-dipping deposit
geometry;
• Very low upfront capital of less than $10M of predevelopment capital; and
• Only 29% of the current Mineral Resource at Western Queen South is included in the mining production
target of this Study, providing additional opportunities to extend Project life and life of mine (LOM)
production.
Scoping Study – Cautionary Statements
The Scoping Study has been undertaken to assess the potential viability of a simple underground mining
operation at Western Queen. It is characterised as a preliminary technical and economic assessment of the
potential viability of mining the Western Queen South deposit and the majority of the relevant parameters
required to be considered. It is based on a lower level of technical and economic assessments that are not
sufficient to support the estimation of ore reserves at Western Queen. As there are no commercial agreements
in place regarding potential mining or processing of gold mineralisation at Western Queen, the Company cautions
that in an overall sense the Study remains at a lower level of economic assessment and thus it has elected to not
characterise it as higher than at scoping study level.
The Production Target generated by the Scoping Study is based upon a deposit comprising 66% Indicated Mineral
Resource category material and 34% Inferred Mineral Resource category material. Investors are cautioned that
there is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty
2 Please refer to the economic parameters and design assumptions listed below from page 12 onwards.
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 3
that further exploration work will result in the determination of Indicated Mineral Resources or that the forecast
production based upon Inferred Mineral Resources will be realised.
At this stage, Ore Reserves have not been estimated, and the Study is insufficient to provide assurance of an
economic development case. Further evaluation work will be required once commercial arrangements for
processing Western Queen ore are finalised and executed, before estimating any Ore Reserves or providing any
assurance of an economic development case.
The Scoping Study is based on the material assumptions detailed which are outlined in this announcement. These
include assumptions about the availability of funding. While Rumble considers all of the material assumptions to
be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of
outcomes indicated by the Scoping Study will be achieved. The Scoping Study referenced in this announcement
has been prepared to assess the potential viability of developing Western Queen and determine whether a
business case can be made before proceeding with more definitive studies.
To achieve the range of outcomes indicated in the Scoping Study, less than $10 million for capital expenditure
and establishment of infrastructure will be required. There is no certainty that Rumble will be able to raise this
amount of funding when required. It is also possible that such funding may only be available on the basis or on
terms that may be dilutive to or otherwise affect the value of Rumble’s existing shares.
This announcement and the Scoping Study have been prepared in compliance with the JORC Code and the ASX
Listing Rules and with reference to ASX Guidance Note 31, ASX November 2016 Interim Guidance Note on
“Reporting scoping studies” and ASIC Regulatory Guide 170. All material assumptions on which the forecast
financial information is based have been made on reasonable grounds. The material assumptions are set out in
this announcement. The Company believes that it has a reasonable basis for providing the forward-looking
statements and the forecast financial information. While the Company considers all the material assumptions to
be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of
outcomes indicated by the Scoping Study will be achieved.
Given the uncertainties involved, investors should not make any investment decisions based solely on the results
of the Scoping Study.
Ore Processing Options
The Western Queen Project is strategically located within 200km of five gold processing mills (see Figure 1).
These are Dalgaranga (2.5 Mtpa), Checkers (2.0 Mtpa), Tuckabianna (1.2 Mtpa), Kirkalocka (2.0 Mtpa) and Golden
Range (0.8 Mtpa).
The Scoping Study assumes off-site processing at Kirkalocka. At this stage the Company does not have a
commercial tolling or ore sale agreement(s) in place. The Company has had ongoing discussions regarding
potential processing arrangements with the owners of several of the processing plants in the area.
The Company signed a non-binding Memorandum of Understanding with Gylden Resources Pty Ltd (“Gylden”)
in October 20253
in relation to the potential to treat Western Queen ore through Gylden’s Kirkalocka plant which
is approximately 180km by road from Western Queen. Gylden has provided a draft ore tolling agreement. Gylden
is planning to refurbish the Kirkalocka plant and recommence operations in the second half of CY2026 processing
third party ores.
The Scoping Study assumes a processing and haulage cost of $100 per tonne, which is based upon conversations
between the Company and consultants with knowledge of other third-party milling agreements in the Eastern
3 Refer to Remble ASX release 22 October 2025 “Western Queen Drilling & Development Update”
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 4
Goldfields and the terms provided by Gylden in the draft ore tolling agreement. The Company believes that this
is a reasonable assumption for this level of scoping study.
The Scoping Study assumes gold recoveries of 94% for all material in a Carbon in Leach (“CIL”) plant. This is based
upon the recoveries attained during mining and processing by previous owners on the fresh material at Western
Queen. Samples will be taken from the current diamond drilling program and metallurgical testwork will be
undertaken on selected samples to confirm the recoveries used in the Study.
As a commercial processing agreement is still pending, the Scoping Study remains at a lower level of economic
assessment and is not characterised at higher than Scoping Study level. Therefore, the estimation of Ore Reserves
is not possible and the Study is insufficient to provide assurance of an economic development case at this stage.
Figure 1. Western Queen tenure and location, relative to local gold processing facilities within 200km
Resources
The Study is based on mining only the Western Queen South high-grade resource. The Mineral Resource
Estimate (“MRE”) which underpins the study has been publicly reported and prepared by Competent Persons as
defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves (“JORC Code”). The MRE was likewise prepared in accordance with the JORC Code. Details are
included in Rumble’s ASX announcement of 23 July 2025.
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 5
Table 1: Western Queen Project Mineral Resources (July 2025)4
Tonnes
(kt)
Grade
(g/t Au)
Ounces Tonne
(kt)
Grade
(g/t Au)
Ounces Tonnes
(kt)
Grade
(g/t Au)
Ounces
Deposit Indicated Inferred Total
Cranes 70 1.4 3,300 70 1.4 3,300
Duke 30 7.2 6,900 4 6.4 800 34 7.1 7,700
WQC 250 7.2 56,600 560 3.8 67,300 800 4.8 124,000
Princess 100 1.9 5,900 380 2.5 30,300 480 2.3 36,200
WQS 830 3.0 78,600 1,490 2.5 120,200 2,320 2.7 198,900
Total 1,210 3.8 148,000 2,510 2.8 222,000 3,720 3.1 370,000
Mining
The Scoping Study is based upon a simple underground design using an uphole stoping method, with a cut-off
grade of 1.5 g/t Au, to mine the high-grade gold mineralisation delineated beneath the Western Queen South
open pit.
Figure 2. Western Queen South Underground Design (Isometric – looking NW)
4
Refer to Rumble ASX release 23 July 2025 “Significant Increase to Western Queen Resources to 370koz @ 3.1g/t Au”
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 6
Scoping Study Accuracy
The Scoping Study has a +/- 30% level of accuracy. All dollar amounts are Australian Dollars unless indicated
otherwise.
The Study has considered the sensitivity of the project’s cumulative discounted cashflow to variations in gold
price and fundamental cost parameters.
Based upon the Mineral Resource Estimate prepared by the Competent Person in accordance with the JORC
Code, the Company characterises this Scoping Study as a detailed technical and economic assessment into the
potential viability of the Western Queen Gold Project for the majority of the relevant parameters required to be
considered. The underground optimisations and mine design are based upon 66% Indicated Mineral Resources,
with the remainder being Inferred Mineral Resources.
There is a low level of geological confidence associated with inferred mineral resources and there is no certainty
that further exploration work will result in the determination of indicated mineral resources or that the
production target itself will be realised.
Project Ownership
The Western Queen South and Central gold deposits sit within granted mining leases M59/45 and M59/208 held
by Western Queen Pty Ltd, which is a 100% wholly owned subsidiary of Rumble. The results of the Scoping Study
are presented on a 100% basis.
Production Target
The Scoping Study generates a “Production Target” as defined in ASX Listing Rule 19.12 as it is presently forecast
that any future production will extend beyond the current and forthcoming financial year. The Company notes
that forecast production is from the Western Queen South deposit only, comprising Indicated Mineral Resources
(66%) and Inferred Mineral Resources (34%). Details of the potential timing of production from Inferred Mineral
Resources are presented under the Underground Mine Plan section of this Study.
Investors are cautioned that there is a low level of geological confidence associated with Inferred Mineral
Resources and there is no certainty that further exploration work will result in the determination of Indicated
Mineral Resources or that the forecast production based upon Inferred Mineral Resources will be realised.
Modifying Factors
The Scoping Study is based on the material assumptions detailed in the section Underground Mine Plan – Inputs
and Assumptions. All relevant modifying factors have been assessed with regard to the proposed extraction by
underground mining methods of a deposit the size and scale of Western Queen South. The various technical
factors and financial inputs are based on the existing site studies, quoted contract costs/rates or direct analogues
from the industry and based upon the personal experience of senior consultants involved in the Study.
Development and Production Schedule
The Western Queen Gold Project and deposits considered in the Study are located on granted mining leases
M59/45 and M59/208.
As announced on 7 October 2025, the Company has commenced a 20,000m diamond drilling program to infill
and extend the current mineralisation at the Western Queen South and Central deposits. As part of this program,
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 7
Rumble intends to collect additional geotechnical and metallurgical information to be utilised in the development
and production schedule.
The gold price applied to the financial inputs to the optimisation and mine design process is based on a range of
A$ gold prices to reflect the expectation that the deposit is accessed. The Company believes that it has a
reasonable basis for making this assumption given the Company’s knowledge and the likely time for grant of all
necessary statutory approvals.
Commercial Agreements
No contracts for and site works mining, ore haulage or processing have been entered into at this stage. All prices
used in the Study are based on a combination of known industry rates, non-binding estimates received from
contractors and the experience of the Study authors.
Project Funding
The Scoping Study includes upfront capital expenditure of less than $10 million primarily for establishment of
the surface infrastructure, open pit dewatering and portal development. At this stage the Company has made no
assumptions about the source of this funding as it would be premature to do so until the project reaches a more
advanced stage, including the execution of the contract mining (if contract mining is chosen) and the ore
processing agreement(s). The Company believes that it is reasonable to assume there will be equity/debt or other
funding available to commence development when required, because:
• the board and management have a track record in project funding (debt and equity);
• the project is in a stable regulatory environment surrounded by established infrastructure;
• the quantum of funding required is relatively small;
• the prevailing spot gold price is well above the estimates for the All in Sustaining Cost; and
• forecast future cash generation is very strong.
If debt is sought, the Company assumes that a working capital facility will be readily available from providers of
such financial instruments and believes that it has a reasonable basis for making this assumption for the same
reasons noted above.
Notwithstanding, there is no certainty that the Company will be able to generate or raise the required amount
of funding when needed. It is also possible that such funding may only be available on terms that may be dilutive
to or otherwise affect the value of the Company’s existing shares. Given the uncertainties noted above, investors
should not make any investment decisions based solely on the results of the Study.
The following sections of this report detail all material assumptions, with further details and important
information also outlined in the Table 6 disclosures contained at the end of this Report.
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 8
Regional Geology
The Western Queen tenements lie within the Archaean Warda Warra Greenstone Belt, a north trending enclave
within the Murchison Province of the Yilgarn Craton. The belt is situated in the far western sector of the Cue
1:250,000 geological map. The Murchison Province has and continues to be a prolific gold producer with over 35
million ounces of gold defined or mined from areas including Never Never-Gilbeys, Mt Magnet, Cue, Mt Gibson,
Meekatharra, and Plutonic. The Warda Warra Greenstone Belt is approximately 35km in length and is up to 7km
wide. The north striking and steeply west dipping Warda Warra Greenstone Belt is a layered sequence that has
been metamorphosed to amphibolite grade and is enveloped by recrystallised granitoids.
Deposit Geology and Mineralisation
At Western Queen, the geology is steep westerly dipping and comprises intercalated sheared amphibolites of
mafic to ultramafic composition with thin iron formation horizons, komatiitic basalt, dolerite sills, and talc
chlorite schists. Later dolerite and pegmatitic felsic intrusives cut across the amphibolites and gold
mineralisation.
Figure 3. Western Queen Project – Tenure, Resources, Prospectivity over 1VD RTP Magnetics
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 9
Structurally, the gold occurrences are interpreted to be associated with these D4 shear zones sub-parallel to
isoclinal upright north striking F3 folds. The north striking and west dipping layered sequence has been
metamorphosed to amphibolite and locally garnet amphibolite grade and is enveloped by recrystallised
granitoids. A later phase of retrograde metamorphism has altered the mineralogy.
Mineralisation is associated with sheared silica-sulphide zones with an ultramafic footwall and a mafic hanging
wall. The mineralised zone is strongly recrystallised and massive, comprising phlogopite-chlorite-tremolite-talc
schist, amphibolite with lenticular quartzo-feldspathic layering and quartz-muscovite-biotite-sillimanite schist.
Pyrite, pyrrhotite, chalcopyrite, molybdenite and scheelite are present. Depth of complete oxidation is
approximately 30 to 60m with depth to fresh rock approximately 45 to 80m. A zone of lacustrine sediments up
to 45m thick overlies the Western Queen South deposit.
Figure 4. Western Queen South – X Section of Geology and MRE Block Model coloured by grade
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 10
Permitting
The current Western Queen resources are located within the granted Mining Leases, M59/208 and M59/45 (refer
to Figure 3).
All the documentation required in relation to obtaining the necessary approvals to allow open pit mining to be
undertaken including the Mining Proposal, Mine Closure Plan, Works Approval and ancillary permits was
submitted to the relevant government departments in June 2025 when the plan was to mine Western Queen
South via open pit. The Company is now working with the relevant government departments to modify the
submissions given the decision to switch to an underground operation.
Additional programs of work to be completed by Rumble for the underground development include:
• Diamond drilling to collect data on rock mass characteristics for geotechnical parameters, which will
assist with detailed mine design in subsequent study phases;
• Supplementary groundwater analysis; and
• Diamond drilling for samples of mineralised intervals for metallurgical testing, including comminution
testing and other physical properties.
Rumble plans to have all the above work finalised by early 2026.
Processing
Rumble do not currently have any commercial agreements in place to process mineralised material from Western
Queen. Rumble does have a non-binding Memorandum of Understanding with Gylden Resources Pty Ltd
regarding the potential to treat Western Queen ore at Kirkalocka and a draft ore tolling agreement has been
provided.
Western Queen is strategically located within 200km of five gold processing plants (refer Figure 1). Details as
follows:
• Kirkalocka (on care and maintenance) owned by Gylden Resources, 180km southeast of Western Queen.
Gylden is about to commence the refurbishment and upgrading of the plant to 2Mtpa capacity, with
operations expected to commence during the second half of CY2026.
• Checkers (operating) owned by Ramelius Resources, as part of the Mount Magnet Gold Project and is
100km southeast of Western Queen. Its current capacity is 2.0Mtpa with Ramelius looking to potentially
increase the capacity to 5Mtpa by FY2028.
• Tuckabianna (operating) owned by Westgold Resources has capacity of 1.4Mtpa, located 110km east of
Western Queen and 24km east of Cue.
• Dalgaranga (on care and maintenance) owned by Ramelius Resources following the acquisition of
Spartan Resources in July 2025. The plant is 48km southeast of Western Queen and has a 2.5Mtpa
processing capacity.
• Golden Range (on care and maintenance) owned by Capricorn Metals is 180km south of Western Queen
and has 800ktpa of capacity.
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 11
Underground Mine Plan: Inputs and Assumptions
Block Model and Mine Design Parameters
The block model used was created with 5m x 1m x 1m blocks, orientated to a strike of 20 degrees. The orebody
wireframe was created at a cut-off grade of 1.0 g/t, with all material outside of this envelope assigned a zero
grade.
The decline was designed at 5.0 x 5.5m, all other waste development at 4.0 x 4.5m, and strike development at
3.0 x 3.5m. Levels were set 20m from floor to floor. All ground support was assumed to be with bolts and mesh
to the grade line. The ore dilution for all ore drives was 5% (at 0.0 g/t Au) with a recovery of 100%.
Stopes were designed with a minimum mining width of 2.5m. Stope dilution was set at 15% (at 0.0 g/t Au) with
a recovery of 85%. This includes a factor for pillars.
Mining is assumed to be carried out with a single twin boom jumbo for all waste development, with two single
boom jumbos for the strike drives.
Underground Mine Layout and Schedule
The Production Target for the Western Queen South underground project is 617kt at 2.95g/t gold for 58.5kozs
contained gold.
The underground mine will be extracting the largely Indicated Resource portion of the orebody immediately
below the Western Queen South open pit.
Figure 5: Western Queen Underground Design – Stage 1 (isometric view) below the existing Western Queen
South pit
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 12
Table 2: Key mine design physicals
Material Type Waste (t) Ore (t) Grade (g/t) Metal (oz)
Measured Resource - - - -
Indicated Resource - 393,000 3.07 38,800
Inferred Resource - 224,000 2.73 19,600
Total 210,000 617,000 2.95 58,500
Investors are reminded that this is not presented as an Ore Reserve estimate due to the lower level of confidence
applied to scoping studies.
Investors are reminded that this is not presented as an Ore Reserve estimate due to the lower level of confidence
applied to scoping studies. The tables may not sum, due to rounding differences.
Mine Scheduling
A life-of-mine schedule was developed based on the physical quantities derived from the underground designs.
The mining sequence has been designed to target the Indicated Mineral Resource before mining the Inferred
Resource.
The full mining schedule spans 32 months and the ore stockpile is assumed to be processed within a month of
extraction. Initially, there is an estimated 6-month lag before full ore stoping commences, after which a
continuous milling feed is maintained throughout the remaining life of mine.
Figure 6: Material movement by resource category (tonnes per month)
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 13
Economic Assumptions and Cost Modelling
Currency and Exchange Rates
All dollar values referred to in this announcement are in Australian Dollars (AUD or A$ or $) unless noted
otherwise.
Royalties
The State Government royalty of 2.5% of revenue per recovered ounce has been applied to the study. A further
third-party royalty of between $6 - $20 per Au oz produced is also included.
Discount Rates and Inflation
A discount rate of 8% has been applied to final net cash flows. The base date used for NPV calculations is the 1
November 2025, with the commencement of underground mining assumed to be second quarter CY2026.
Operating Costs
A cost model has been developed, incorporating mining costs, personnel expenses, and fixed and variable rates.
The model provides a detailed estimate of the Western Queen operating costs and has been benchmarked
against comparable operations of similar size and type within Western Australia.
Table 3: Mining and Owner’s Costs assumptions
Diesel 1.10
$ /litre
Development (inc support)
3.0 x 3.5 Dev (3 H) 2,378
$ /m
4.0 x 4.5 Dev (4 H) 2,786
$ /m
5.0 x 5.5 Dev (5 H) 3,302
$ /m
Bogging
Conventional inc diesel 8.60
$ /t
Remote inc diesel 9.66
$ /t
Haulage
Haulage inc diesel 4.22
$ /tkm
Fixed Costs
Underground 305,000
$ /month
Surface / client 450,000
$ /month
Other
2m Rise 3,280
$ /m
4m Rise 2,953
$ /m
Stripping 25.00
$ /t
Stoping Total 23.79
$ /t
Contingency allowed 20%
On all costs except Surface Fixed
Mining Costs
Rumble Resources Limited
ASX:RTR
ABN 74 148 214 260
rumbleresources.com.au
T: +61865553980
E:info@rumbleresources.com.au
HeadOffice
Level1, 16 OrdSt
WestPerth, WesternAustralia6005 14
Mining costs have been developed from advised mining contract rates. The diesel price was set based on current
prices allowing for transport to site, rent of facilities, and allowing for the government diesel rebate.
Fixed costs are to allow for salaries, power supply and accommodation and flight costs.
A contingency has been included to allow for miscellaneous dayworks, grade control and other costs which have
not been fully developed.
A combined processing and ore haulage cost of $100 per ore tonne has been assumed. This rate will co